Mining News Pro - Canada’s Ivanhoe Mines (TSX:IVN) said on Monday that progress at its Kakula copper project, the first of multiple planned mining areas at Kamoa-Kakula in the Democratic Republic of the Congo (DRC) continues ahead of schedule.
The company, together with its joint venture (JV) partner China’s Zijin Mining Group, has now completed more than 17 km of underground development, of which 5.1 kms is ahead of schedule.
Ivanhoe also said that Kakula’s 2,000-tonne-per-hour ore conveyor system began operations in June, which will further increase the mine’s pace of underground development.
As work on extending the mine below the surface progresses over the next few months, the majority of the headings are expected to transition into the high-grade ore zones, Ivanhoe said.
The Vancouver-based miner noted that early implementation of covid-19 prevention measures has allowed the development of Kakula to continue uninterrupted. As a result, initial production is expected in the third quarter of 2021.
Cost increase
In November, the Kamoa-Kakula team completed basic design and costing for Kakula’s initial mine and infrastructure, the first concentrator module and associated infrastructure.
The report pushed initial capital costs up to about $1.3 billion — an 18% increase over planned costs.
Billionaire Robert Friedland, who made his fortune from the Voisey’s Bay nickel project in Canada in the 1990s, has been working on Kamoa-Kakula for ten years.
The mining legend believes the project, being developed in partnership with China’s Zijin Mining Group, will become the world’s second-largest copper mine.
According to an independent pre-feasibility study (PFS) released last year, if all phases are completed the operation is expected to reach peak annual production of more than 700,000 tonnes of copper.
The updated resource estimate for the massive project, delivered in February, shows it holds 1.4 billion indicated tonnes grading 2.74% copper for 83.7 billion pounds of copper and another 339 million inferred tonnes grading 1.68% copper for 12.5 billion pounds of copper at a 1% cut-off grade.
Ivanhoe’s stock was up 3.6% on the TSX on Monday afternoon. The company has a C$4.9 billion market capitalization.
Short Link:
https://www.miningnews.ir/En/News/561689
Top copper producer Codelco reported a decline in quarterly output due to lower quality ore at its aging Chilean mines — ...
When former boss Mark Cutifani left Anglo American Plc in mid-April 2022, things had rarely looked better for the ...
Chile President Gabriel Boric said on Thursday he is targeting an increase in the country’s annual copper output by 1 ...
Brazilian miner Vale SA sees no impact from BHP Group’s bid for Anglo American on the latter’s Minas-Rio project, its ...
Copper miner Antofagasta Plc is holding meetings with investors this week for its first dollar bond offering in nearly ...
Copper needs to reach $12,000 a ton — a 20% jump from this week’s high — to incentivize large-scale investments in new ...
Teck Resources, Canada’s largest diversified miner, saw its copper production jump by 74% in the first three months of ...
Aurubis AG, Europe’s largest refined copper producer, has started a project in its Bulgarian smelter which will expand ...
Anglo American Plc said it is has received an unsolicited non-binding combination proposal from BHP Group.
No comments have been posted yet ...