Mining News Pro - A “wild swing” in the Mexican peso weighed on Torex Gold‘s (TSE: TXG) first quarter, despite solid production of 108,537 ounces of gold at the company’s El Limon Guajes mining complex in Guerrero state.
Torex president and CEO Fred Stanford noted that accounting changes in the treatment of stockpiled ore and the depreciation in the peso – by nearly 25% during the quarter – meant higher costs.
“For the quarter, the accounting changes to stockpiled ore resulted in an increase of approximately $100 per ounce to total cash costs and all-in sustaining costs,” Stanford said.
“This impact will decline over the coming quarters and is expected to average out at the impact expected in the original annual guidance numbers. The US monetary stimulus in reaction to covid-19 resulted in the depreciation in many emerging market currencies, including Mexico’s. This has us offside with our currency hedges and when ‘marked to market,’ the significant lost opportunity to benefit from the depreciated peso, affected earnings.”
The Mexico-focused miner reported a net loss of $47 million on revenue of $172 million for the quarter, compared with a net loss of $1.3 million on revenue of $101.9 million in the same period of 2019.
Adjusted net earnings were $19.9 million. The company reported total cash costs of $794 per oz. and AISC of $975 per oz.
The El Limon Guajes complex, Torex’s only producing mine, is located 180 km southwest of Mexico City.
The mine was shut down for planned maintenance at the end of the quarter when the Mexican government ordered the temporary suspension of non-essential businesses, including gold mining, in response to the covid-19 pandemic.
Exploration drilling at El Limon Guajes and the company’s nearby Media Luna project was also suspended.
Torex continues to pay its employees during the suspension.
In late April, the company drew C$50 million on its revolving loan facility to provide additional liquidity during the suspension.
The company ended April with C$134.8 million in cash and has now drawn C$100 million on the C$150 million facility.
Stanford, who is stepping down as CEO and will be replaced by Jody Kuzenko at the company’s next annual meeting, said the suspension of operations could be lifted by May 18. Stanford will remain on the company’s board as executive chair.
Torex withdrew its guidance for the year on April 2 and says it can’t provide new guidance until it has more certainty around the suspension.
Torex’s stock was down 7.3% on the TSX Wednesday afternoon. The company has a C$1.6 billion market capitalization.
Short Link:
https://www.miningnews.ir/En/News/525684
South African diversified miner Sibanye Stillwater is discussing with lenders to temporarily lift limits on borrowings, ...
London-based Savannah Resources will if necessary ask Portugal’s government to authorize compulsory land acquisitions ...
Africa-focused Montage Gold announced Thursday it has received a ministerial order granting all environmental approvals ...
Newmont Corp. has no plans to expedite a decision on its $2.5 billion Yanacocha Sulfides project, dashing the Peruvian ...
Imports of iron ore by China, the world’s biggest buyer, in 2024 are expected to be around 1.17 to 1.18 billion metric ...
China’s central bank added 60,000 troy ounces of gold to its reserves in April, official data showed on Tuesday, ...
First Quantum Minerals said on Monday it is looking forward to talks with Panama’s new government to find a resolution ...
BHP has put South Africa and its mining sector on the spot. The $140 billion Australian group’s ambitious swoop on rival ...
Gold rose after mixed signals from the US, where optimism is growing the economy is on target for a soft landing as the ...
No comments have been posted yet ...